The Car Park Project

The architects and design engineers working on our project to install a new Sustainable Drainage System (SUDS), replace the drains from the Village Hall and re-surface the car park have now completed their re-design. This work was required by the Borough Council as part of the planning consent and will help to drive down costs. We will start the tender competition in the next few weeks to select a contractor to deliver the project. We have specified that the work will need to take place in July and August, traditionally a quieter period for the Hall, as the excavations in the car park will mean that the building will not be accessible for 5 or 6 weeks. I’ll will let you know when a contractor has been appointed.

Gareth Jones

Chairman, Bramley Village Hall Trust